HOTEL FF&E / PROCUREMENT GUIDE

From mock-up room to phased furniture delivery

Bring appearance, dimensions and site conditions into one controlled production basis before release.

01

Create a common item and revision system

Connect room types and areas to item codes, drawing numbers and sample references. Record the date, author and approval status of each revision, including when superseded information is withdrawn. A common register lets design, purchasing, production and site teams identify the same item without relying on informal descriptions or photographs alone.

02

Confirm measurement responsibilities and datums

For cabinetry, wall panels, door surrounds and headboards, establish finished surfaces, levels, substrate conditions and installation space. Agree who provides dimensions, who verifies them, when measurement can take place and who approves release dimensions. Recheck affected items after site changes instead of assuming an earlier survey still describes the finished room.

03

Draw the interfaces, not only the elevation

Coordinate sockets, lighting, equipment access, basin cut-outs and stonework boundaries in the developed details. Check door swings, drawer clearance, skirting and corners together. Assign each opening, connection and final junction to a trade. Equipment or architectural elements visible in a reference photograph do not automatically become part of the furniture package.

04

Review the mock-up as a working room

Review more than colour and appearance. Check table-to-seat relationships, arm clearance, bedside access, cabinet opening, hardware operation and cleaning access. Convert comments into controlled drawing, material and schedule revisions, and agree whether another sample is needed. The approved mock-up should be a repeatable reference for later rooms, rather than an isolated display piece.

05

Carry approvals through packing and handover

Link production, inspection, packing labels and packing lists to the same area and item codes. Agree inspection criteria, sampling or buyer inspection, batch records and receiving checks in advance. Coordinate unloading, storage, installation responsibilities and protection with the site programme so the release of a production batch matches a usable receiving plan.

General procurement coordination guidance. It does not replace local professional design, testing, statutory requirements or the project agreement.

Get FF&E Project Quotation ↗

LET’S START WITH YOUR BRIEF

Tell us what you are building.

Send the destination, space types, estimated quantities and target delivery date, together with a furniture schedule or drawings. We will review the supply scope, materials, samples, production planning and site coordination. Reference images are welcome while the design is still developing.

Start with your project location, furniture scope and target dates. We can help identify the information needed for the next step.

Add delivery & testing requirements (optional)
Drawings & schedulesOptional

Share layouts, furniture schedules or reference images. Contact us on WhatsApp to discuss larger drawing packages.

    Materials are used for project communication. Upload only files you are authorised to share and omit unrelated personal information.

    Use of project information

    Your contact details, brief and attachments are used by W.H staff to assess requirements, prepare quotations and follow up on the project. Email us below to request a correction or deletion. Do not upload sensitive information unrelated to your enquiry. Enquiry-source information is also used for business analysis.

    odix.furniture@zohomail.cn
    Chat on WhatsApp